Developing the project schedule is often an iterative process. It determines the planned s
公共英语
已帮助 人
Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to
(75) progress.
(75)
A. analyze
B. track
C. level
D. extend
请帮忙给出正确答案和分析,谢谢!