Estimating activity durations uses information on activity scope of (74) required resourc

计算机 自考英语 已帮助 人

Estimating activity durations uses information on activity scope of (74), required resource types, estimated resource quantities, and resource calendars.

(74)

A. milestone

B. baseline

C. quality

D. work

请帮忙给出正确答案和分析,谢谢!