The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that __(74)__.

(74)A.the project is ahead of its planned schedule

B.less work was completed than was planned

C.the cost overrun for work completed

D.the cost under-run of performance to date

热搜:投资利率系数对is曲线的影响

答案解析

难度★★☆ 搜索
  • 参考答案:B参考译文挣致分析技术是一种综合了范围、成本、进度指标的常用绩效测量方法。它帮助项目团队评价项目绩效。如果一个项目的进度绩效指数SPI值小于1,意味着(74)。(74)A.进度超前B.进度滞后C.成本超支D.成本结余根据《系统集成项目管理工程师教程》(全国计算机专业技术资格考试办公室组编)第9.5.3小节的内容可知,SPI值小于1表示实际进度落后于计划进度。因此,正确答案应选B。参考答案(74)B