A project manager believes that modifying the scope of the project may provide added value service for the customer.The project manager should______.

A.assign change tasks to project members

B.call a meeting of the configuration control board

C.change the scope baseline

D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

热搜:a是b的充分条件,b是a的必要条件吗

答案解析

难度★★☆ 搜索
  • 正确答案:D
    解析:项目经理认为调整项目范围可以给客户提供增值的服务,项曰经理应该怎么做。
    选项A是安排任务变更到项目成员,选项B是召集变更控制委员会会议,选项C是变更项目基线,选项D是按照原先的基线,在确定完成一项改进项目会得到客户的相应资金前,暂缓修改。
    由于是在原内容基础上增加增值服务内容,超出原先范围,应先确定客户认可和增加新资金,因此应选择D。