A project manager believes that modifying the scope of the project may provide added value service for the customer .The project manager should()()A. assign change tasks to project membersB. call a meeting of the configuration control boardC. change the scope baselineD. postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

热搜:a是b的充分条件,b是a的必要条件吗

答案解析

难度★★☆ 搜索
  • 参考答案:D项目经理认为调整项目范围可以给客户提供增值的服务,项目经理该怎么做。选项D是按照原先的基线,在确定完成一项改进项目会得到客户的相应资金前,暂缓修改。由于是在原内容基础上增加增值服务内容,超出原先范围,应先确定客户认可和增加新资金,因此应选择D。